| 2009 |
Jan.
Start-up Contract for UAE Shuweihat S2 Project
Feb. Zero disaster rate for 28
Years in Seoul Thermal Power Plant
May. Awarded 'Coal-fired Top Plant
Awards' at the 2009 USA Power Award
Jun. Construction of Boryeong Thermal
Power Plant Unit No.7,8 Completed
Sep. Construction of Boryeong Small
Hydro Power Plant completed
Long Term Trouble
free operation for 10years(3653days) at Boryeong
Thermal Power Plant Unit No.3
Nov. Construction of Jeju Internal
Combustion Power Plant completed
Zero disaster
rate for 27years in Jeju Thermal Power Plant
Dec. Construction of Incheon Combined-cycle
Power Plant Unit No.2 completed |
| |
| 2008 |
Mar. Construction
of Seocheon renewable energy theme park and photovoltaic
power plant completed Sep. Trouble
free operation for 1,000days at Boryeong Thermal
Power Plant Unit No.4
Oct. Awarded Best Operation & Maintenance
Project in Asia at the 2008 Asian Power Awards
Dec. Trouble free operation for
1,000days at Jeju Thermal Power Plant Unit No.2
|
| |
| 2007 |
Mar.
Awarded Grand Prize at the 2006 Industrial safety
management awards Oct. Trouble
free operation for 3,000days at Boryeong Thermal
Power Plant Unit No.3 |
| |
| 2006 |
Mar.
Completion of [BLUE JB]total information system
Aug. Obtained Hyundai Steel Waste
Gas BOO project contract Jun.
Construction of Yangyang Wind Power Plant completed
Sep. Construction of Yangyang Pumped-Storage
Power Plant completed Sep.
Registered sustainability report on UN GRI |
| |
| 2005 |
Sep.
Construction of Yangyang small hydro power plant
completed Nov. Construction
of Incheon combined-cycle power plant and Jeju internal
combustion power plant completed Dec.
Order for power plant operation and maintenance
project in Lebanon secured Dec.
Installation of NOx-reducing facility at Seocheon
Thermal Power Plant |
| |
| 2004 |
Mar. 'JB Power Vision 2008 Strategy'
declared Dec. Company-wide
integrated certification of ISO 9001/14000(quality
and environment management system)obtained
for the entire company |
| |
| 2003 |
| Placed 1st in the 2003
Power Company Management Evaluation organized by
KEPCO (among 6 power generation companies in KOREA)
|
| |
| 2002 |
Nov.
Construction of Boryeong Combined-Cycle Power Plant
was completed Dec. Installation
of De-Nitrification facilities at Seoul Thermal
Power Plant |
| |
| 2001 |
| Apr. Korea
Midland Power Co.,Ltd(KOMIPO) was incorporated through
a spin off of KEPCO |